one common mistake made early in the risk identification process is to

Hi, I have a question and I hope anyone could answer it:

One common mistake made early in the risk identification process is to

A. Not all possibilities are considered

B. Participants are over-optimistic

C. Participants are over-pessimistic

D. Focus on objectives and not on the events that could produce consequences.

E. Too much attention is given to past events

Related Questions

You must login to add an answer.

1 Answer

  1. D. Focus on objectives and not on the events that could produce consequences.